Development Process

The Montgomery County Planning Board’s Department of Park and Planning's Development Review division coordinates the timely review of proposed development projects. Below is a listing of past and future anticipated events for Falkland North.

  • Mid-May 2010 – submit amended project plan/preliminary plan
  • Mid-June 2010 – submit final package
  • July 26, 2010 – Development Review Committee
  • September 16, 2010 – project plan/preliminary plan hearing
  • 2Q11 – final site plan hearing
  • 3Q11 – submit for building permit (first phase)
  • 1Q12 – potential construction start
  • 4Q10 - project/preliminary plan hearing
  • 4Q13 – potential opening of first phase
  • 3Q14 - potential completion of first phase
  • 1Q14 – construction complete (first phase)

Click here to access M-NCPPC then enter application #920070080.

 